Acceptance Test Disagreements — When Roll Forming Machine FAT & SAT Results Don’t Match Expectations
Acceptance testing is supposed to prevent disputes.
Acceptance testing is supposed to prevent disputes.
Yet in the roll forming industry, Acceptance Test Disagreements are one of the most common causes of commercial conflict between buyer and supplier.
Typical scenarios:
-
Machine passed factory test — but fails onsite
-
Performance at FAT was higher than at SAT
-
Speed achieved in factory cannot be repeated
-
Profile dimensions differ from approved samples
-
Punch alignment shifts after installation
-
Buyer refuses final payment due to performance concerns
At the center of these disputes are two critical terms:
-
FAT — Factory Acceptance Test
-
SAT — Site Acceptance Test
When expectations are not clearly defined in contract, disagreements become inevitable.
This guide explains:
-
What FAT and SAT really mean
-
Why results differ
-
When warranty applies
-
When responsibility shifts to site conditions
-
How to protect your position
What Is a Factory Acceptance Test (FAT)?
A FAT is performed at the manufacturer’s facility before shipment.
It typically verifies:
-
Machine runs mechanically
-
Profile matches drawing
-
Punch locations correct
-
Cut length within tolerance
-
Electrical system functional
-
Safety circuits operational
-
Production speed demonstrated
FAT conditions are usually:
-
Controlled material
-
Stable power supply
-
Factory-trained operators
-
Ideal setup conditions
FAT proves the machine functions — but not necessarily under every site condition.
What Is a Site Acceptance Test (SAT)?
SAT occurs after installation at buyer’s facility.
It verifies:
-
Machine installed correctly
-
Electrical supply compatible
-
Foundation stable
-
Local material compatible
-
Production meets contractual performance
SAT is where most disputes arise.
Why?
Because site variables introduce new factors.
Why FAT and SAT Results Often Differ
1. Different Material Used
At FAT:
-
Certified material within spec
At SAT:
-
Local coil
-
Higher tensile
-
Thickness variation
-
Width inconsistency
Material differences dramatically affect performance.
2. Electrical Supply Variation
Factory power is stable and balanced.
Site power may have:
-
Voltage drop
-
Phase imbalance
-
Frequency fluctuation
This affects:
-
Servo stability
-
Motor torque
-
Hydraulic performance
3. Installation & Leveling Differences
Factory setup is:
-
Precision leveled
-
Properly shimmed
-
Optimally aligned
Site installation may introduce:
-
Frame twist
-
Uneven anchoring
-
Floor flex
This impacts product quality and vibration.
4. Operator Experience
Factory operators:
-
Know optimal settings
-
Understand roll progression
Site operators may:
-
Adjust incorrectly
-
Overtighten stands
-
Alter parameters
Training gaps create perceived “performance loss.”
5. Environmental Differences
Temperature, humidity, dust, and vibration affect:
-
Electrical components
-
Hydraulic systems
-
Material behavior
Factory conditions are controlled — site conditions may not be.
Common Acceptance Test Dispute Scenarios
Scenario 1: Speed Achieved at FAT but Not at SAT
Buyer claims machine cannot reach contracted speed.
Investigation reveals:
-
Higher tensile material
-
Conservative servo tuning
-
Hydraulic pressure reduced
Responsibility depends on contract-defined speed conditions.
Scenario 2: Profile Dimensions Different Onsite
Factory sample approved.
Onsite panels slightly out of tolerance.
Cause may include:
-
Material variation
-
Installation twist
-
Setup differences
Mechanical defect must be proven before warranty applies.
Scenario 3: Punch Alignment Correct at FAT, Misaligned at SAT
Potential causes:
-
Strip width variation
-
Encoder recalibration
-
Frame flex
-
Installation misalignment
Responsibility depends on root cause.
When Acceptance Test Disputes Become Warranty Claims
Warranty may apply if:
-
Machine cannot meet agreed tolerance under defined conditions
-
Performance guaranteed in contract
-
Material and installation match specification
-
Mechanical defect identified
Warranty may not apply if:
-
Conditions at SAT differ from FAT
-
Material differs from approved specification
-
Installation not compliant
-
Parameters modified without authorization
Contract clarity is critical.
The Importance of Written Performance Specification
To avoid disputes, contract must define:
-
Material thickness range
-
Tensile strength range
-
Strip width tolerance
-
Production speed definition
-
Dimensional tolerance
-
Whether punching included in speed rating
-
Acceptance criteria
Without written criteria, disagreements become subjective.
Structured FAT & SAT Protection Checklist
Before FAT
-
Define performance criteria in writing
-
Confirm material specification
-
Confirm speed definition
-
Agree measurement method
-
Record full FAT video
-
Sign FAT approval document
Before SAT
-
Confirm electrical supply matches specification
-
Confirm foundation compliance
-
Use certified material
-
Reconfirm PLC baseline parameters
-
Ensure trained operator present
-
Document SAT results clearly
Real Case Example
A 30 m/min structural machine achieved 30 m/min at FAT.
At SAT, maximum stable speed was 24 m/min.
Buyer withheld payment.
Investigation revealed:
-
Site material tensile 18% higher than FAT material
-
Motor operating at near full torque
-
Frame vibration increased
Under contracted material spec, machine met performance.
Dispute resolved in supplier’s favor.
Second case:
Roofing line approved at FAT with 1000 mm cover width ±1 mm.
At SAT, width tolerance ±4 mm.
Material confirmed correct.
Inspection revealed:
-
Frame base twisted during installation
-
No proper shimming
After re-leveling, tolerance returned to ±1 mm.
Root cause: installation error.
Warranty claim rejected.
Third case:
Punching line passed FAT.
At SAT, hole alignment consistently off by 2 mm.
Material and installation verified correct.
Inspection revealed punch frame deflection under load.
Design reinforcement required.
Warranty claim approved.
Signs Acceptance Dispute Is Site-Related
-
Performance varies by coil
-
Vibration increases at higher speed
-
Electrical alarms inconsistent
-
Issues improve after re-leveling
Likely SAT condition difference.
Signs It May Be Manufacturing Defect
-
Same issue reproducible at factory
-
Mechanical measurement shows tolerance error
-
Machine cannot meet stated spec under agreed conditions
-
Defect independent of material or installation
Likely warranty responsibility.
Frequently Asked Questions
What is the difference between FAT and SAT?
FAT is factory testing before shipment. SAT verifies performance after installation onsite.
Can performance differ between FAT and SAT?
Yes. Material, electrical supply, and installation differences affect results.
Should acceptance criteria be written in contract?
Absolutely. Without written criteria, disputes are difficult to resolve.
Can buyer refuse final payment due to SAT performance?
Yes — if machine fails to meet contract-defined criteria.
Is supplier responsible for site conditions?
Typically no — unless installation and commissioning included in contract.
What is the biggest cause of acceptance disputes?
Unclear performance definitions in contract.
Final Conclusion
Acceptance test disagreements are rarely about bad faith — they are about unclear expectations.
Most disputes arise because:
-
Material not defined clearly
-
Speed not defined precisely
-
Tolerances not written
-
Installation conditions not verified
-
FAT and SAT criteria not aligned
A roll forming machine may perform perfectly at factory — yet fail at site due to environmental or setup differences.
Clear contract terms, documented testing, and structured verification prevent costly disputes.
Without written acceptance criteria, disagreements become subjective.
With structured FAT and SAT documentation, liability becomes clear.